Finding Risks: Techniques for Identification

You can't respond to a risk nobody has written down. Identification is the step that produces the list everything else works from: a set of candidate risks, each with a cause, a trigger that would show it starting to happen, and a first guess at its category. It's also the step most easily done badly, because the obvious risks come quickly and give a false sense of completeness.the obvious ones are the least likely to surprise you

The techniques below fall into two families. Team-based techniques draw risks out of people's heads; analytical techniques draw them out of documents, history and structure. Both are needed, and both work better with a wide range of people involved: developers, testers, users, operations staff and the client each see different failure modes. After those come three ways of tracing causes, a way of sorting risks by how knowable they are, and two worked examples.

Write a Risk as Cause, Event and Consequence Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

A risk written as a single noun ("security", "the database", "time") can't be estimated, owned or acted on. A risk written as a sentence with three parts can:

Because [cause], [uncertain event] may happen, which would lead to [consequence for an objective].

VagueUsable
"Staffing"Because only one developer understands the deployment scripts, a release may stall if they're unavailable, which would delay the beta by one to two weeks.
"Performance"Because search runs a full table scan, response times may exceed 2 seconds once the catalogue passes 50,000 items, which would fail the agreed usability criterion.
"Third-party API"Because we depend on version 2 of the provider's API, a deprecation notice may arrive before launch, which would force unplanned migration work.

The cause tells you where to act. The event tells you what to watch for. The consequence tells you how much it matters, and in which units, which is what Measuring Risk needs.consequence must be measurable to compare risks

Team-Based Techniques Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

TechniqueHow it worksStrengthWeakness
BrainstormingFacilitated, free-form generation; no criticism until the list is completeFast, cheap, builds shared awarenessLoud voices and seniority dominate; the group converges early
Delphi techniqueExperts respond anonymously in rounds, see a summary of the others' answers, and reviseRemoves status effects; works across sitesSlow; needs a careful facilitator
InterviewsStructured questions to stakeholders one at a timeReaches people who won't speak in a group; finds domain risks the team can't seeTime-consuming; quality depends on the questions
Pre-mortemThe team imagines the project has already failed and writes down whyGives permission to voice doubts; finds risks optimism hidesCan drift into pessimism without facilitation

The Delphi method came out of RAND in the early 1960s as a way of reaching a consensus of expert opinion through a series of questionnaires with controlled feedback between rounds1. Anonymity is the active ingredient. A junior developer who suspects the architecture won't scale is far more likely to say so on an anonymous form than across a table from the architect.

The pre-mortem, described by Klein, reverses the usual framing: instead of asking "what might go wrong?", the leader announces that the project has failed and asks each person to write down the reasons2. It draws on research into prospective hindsight, which found that the way people explain an event changes when they imagine it as having already happened rather than as something that might happen3. Klein also points out a side effect: a team that has run a pre-mortem is primed to notice early signs of trouble once the project is under way.framing shapes what we see

This is the approved approach. Start a session with silent, individual writing before any discussion. Brainstorming, Delphi and pre-mortems all produce more, and more varied, risks when people commit their own list before hearing anyone else's.

Analytical Techniques Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

TechniqueHow it worksStrengthWeakness
ChecklistsWalk through a list of risks seen on past projectsCheap; catches the common cases nobody thinks to mentionOnly finds what has happened before; encourages box-ticking
SWOT analysisStrengths, Weaknesses (internal), Opportunities, Threats (external)Finds opportunities as well as threats; links risks to the team's own capabilityCoarse; items need rewriting as causeโ€“eventโ€“consequence afterwards
Assumptions analysisList every assumption in the plan, then ask how sure you are of each and what happens if it's falseTurns hidden beliefs into explicit risksAssumptions are hard to see from inside; works best with an outsider asking
Document reviewRead requirements, contracts, architecture notes looking for ambiguity, gaps and dependenciesFinds risks in the agreed baseline before work startsOnly as good as the documents

Two published checklists are worth knowing. Boehm's top-10 list of software risk items, built from a survey of experienced project managers, pairs each item with the techniques that had worked against it4. DeMarco and Lister later argued that five core risks account for most of the trouble on software projects: an inherent flaw in the schedule, requirements inflation, personnel turnover, specification breakdown, and under-performance5. The tagging in the right-hand column below is ours, not Boehm's; it shows how many of his "technical" items have their roots in how the work is organised.

#Boehm's risk itemProcess or product?
1Personnel shortfallsProcess
2Unrealistic schedules and budgetsProcess
3Developing the wrong functions and propertiesProduct (caused by weak requirements process)
4Developing the wrong user interfaceProduct (caused by too little user involvement)
5Gold-platingProcess creating product risk
6Continuing stream of requirements changesProcess
7Shortfalls in externally furnished componentsProduct (via supplier)
8Shortfalls in externally performed tasksProcess (via supplier)
9Real-time performance shortfallsProduct
10Straining computer-science capabilitiesProduct

The list dates from 1991, and some items read differently now: "externally furnished components" today means open-source dependencies and cloud services as much as contracted hardware. Use any checklist as a prompt, then add your project's own history to it. The risks that bit the last project are the best checklist the next one can have.checklists miss unknown unknowns

Tracing Causes Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

A risk list often records symptoms. Tracing back to causes matters because responses work on causes; mitigate a symptom and the same cause produces a different symptom next month.cf. debugging: tracing from symptom to cause

Five Whys

Associated with the Toyota Production System6, the technique asks "why?" repeatedly until a cause appears that the team can act on:

  1. Why did the release slip? Testing took longer than planned.
  2. Why? Many defects were found late.
  3. Why? Code reviews had been skipped.
  4. Why? The team was under time pressure.
  5. Why? The schedule was unrealistic from the start.

The chain starts with a product symptom (defects) and ends at a process cause (estimation). That's typical, and it's why improving estimation, rather than adding a testing phase, is the response that stops it recurring.

The technique has known limits. Card's review of its use in healthcare root-cause analysis argues that it forces a single linear chain onto events that usually have several interacting causes, that where it stops is arbitrary, and that two people asking the same questions often reach different "root" causes; he suggests it suits teaching better than serious investigation7. Use it to get a team thinking causally, then switch to a diagram that allows more than one branch.

Cause-and-Effect (Fishbone) Diagrams

Ishikawa's cause-and-effect diagram places the effect at the head and groups possible causes along bones by category8. For a software risk, categories split naturally between process and product:

graph LR subgraph Process P1["People:
one person knows deploy"] P2["Method:
no code review under pressure"] P3["Estimation:
no buffer for integration"] end subgraph Product T1["Design:
tight coupling to vendor API"] T2["Technology:
new framework, little experience"] T3["Environment:
staging differs from production"] end P1 --> E["Effect:
release slips
with critical defects"] P2 --> E P3 --> E T1 --> E T2 --> E T3 --> E style E fill:#FFC857

Each bone is a candidate risk in its own right, and the diagram makes it obvious when one category is empty because nobody thought to look there.

Influence Diagrams and Process Flowcharts

Influence diagrams, formalised by Howard and Matheson, show decisions, uncertain quantities and outcomes as nodes, with arrows for the relationships between them9. They're useful when risks interact, because the arrows show which uncertainty feeds which:

graph LR D["Decision:
adopt new framework?"] --> L["Uncertain:
team learning time"] D --> P["Uncertain:
framework performance"] L --> S["Uncertain:
schedule slip"] P --> Q["Uncertain:
meets response-time target"] S --> V{"Outcome:
project value"} Q --> V

A process flowchart does a similar job for a workflow: draw the steps from commit to production, then mark every hand-off and manual step as a candidate failure point.

Known, Unknown and Unpredictable Risks FoundationalKnowledge that endures for decades โ€” core principles

TypeDescriptionHow to manage
KnownIdentified and understoodSpecific responses, owners, triggers
UnknownForeseeable, but nobody has identified it yetChecklists, reviews, outside perspectives, regular re-identification
UnpredictableRare, high-impact events that couldn't reasonably have been foreseenManagement reserve, and designs that degrade gracefully

Taleb's "black swan" names the third category: an outlier, beyond regular expectations, with extreme impact, which people explain after the fact as if it had been predictable10. You can't list black swans in a register by definition. What you can do is build systems and plans that don't collapse when one arrives, which is where architectural resilience (see engineering practice as standing mitigation) earns its place.

Identification effort pays best on the middle row. Every identification session moves some unknown risks into the known row; the measure of a good session is how many it moves.move means: spot it, name it, add to register

Worked Example: An Individual Project Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

A student starting a major coursework project lists risks quickly: data loss, a laptop failure, missed deadlines, an unavailable partner, no access to a resource. Rewritten as causeโ€“eventโ€“consequence and split by where each one lives, the list looks like this:

RiskProcess or productObvious response
Because work is only on one laptop, a disk failure may lose weeks of work, delaying submissionProcessVersion control with a remote; this alone removes most of the impact
Because three deadlines fall in week 9, the project may get no time that week, compressing testingProcessMove testing earlier; plan week 9 as a gap
Because my partner also has a placement interview cycle, they may be unavailable for integration, delaying the demoProcessAgree integration dates now; define interfaces so each half runs alone
Because the dataset licence hasn't been confirmed, access may be refused, removing the evaluationProductRequest confirmation now; identify a public fallback dataset
Because I've never used this library, it may not support the feature I need, forcing a redesignProductBuild a one-day spike before committing the design
Because the evaluation needs participants, recruitment may fall short, weakening the resultsProductRecruit early; design an evaluation that works with fewer participants

Most of the first list was process risk. Adding the product rows usually needs a second pass with a different question: not "what could stop me finishing?" but "what could make what I finish wrong?" Risk Analysis for a Project takes this example further.product risk: the thing is wrong, not just late

Worked Example: A Software Project Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

SourceExampleCategory
VendorA third-party component is delivered late or doesn't meet its specificationProcess (schedule) and product (quality)
PersonnelA critical developer leaves mid-projectProcess
ScopeRequirements keep changing after design is agreedProcess
TechnicalTwo subsystems fail to integrate under production loadProduct
InfrastructureA data-centre outage or regional disaster takes services offlineProduct (availability)
OrganisationalProject sponsorship changes hands and priorities shiftBusiness
Practical exercise. Take a project you're working on now. Spend five minutes writing risks alone, then run a two-minute pre-mortem: "it's the deadline, and the project has failed; why?" Rewrite every item as causeโ€“eventโ€“consequence and tag it process, product or business. Which column is thinnest, and what question would fill it?

From List to Register Applied / MethodologicalKnowledge with a 5โ€“10 year half-life โ€” stable practice

Each identified risk becomes a row in the risk register: an ID, the causeโ€“eventโ€“consequence description, a category, a trigger and a provisional owner. Probability, impact and exposure come next, in Measuring Risk. Identification doesn't end there; it's repeated at every review, because new risks appear as the project learns more (see Keeping Risk Management Alive).

References


  1. Dalkey, N., & Helmer, O. (1963). An experimental application of the Delphi method to the use of experts. Management Science, 9(3), 458โ€“467. https://doi.org/10.1287/mnsc.9.3.458 โ†ฉ

  2. Klein, G. (2007). Performing a project premortem. Harvard Business Review, September 2007. https://hbr.org/2007/09/performing-a-project-premortem โ†ฉ

  3. Mitchell, D. J., Russo, J. E., & Pennington, N. (1989). Back to the future: Temporal perspective in the explanation of events. Journal of Behavioral Decision Making, 2(1), 25โ€“38. https://doi.org/10.1002/bdm.3960020103 โ†ฉ

  4. Boehm, B. W. (1991). Software risk management: Principles and practices. IEEE Software, 8(1), 32โ€“41. https://doi.org/10.1109/52.62930 โ†ฉ

  5. DeMarco, T., & Lister, T. (2003). Waltzing with Bears: Managing Risk on Software Projects. Dorset House. โ†ฉ

  6. Ohno, T. (1988). Toyota Production System: Beyond Large-Scale Production. Productivity Press. โ†ฉ

  7. Card, A. J. (2017). The problem with '5 whys'. BMJ Quality & Safety, 26(8), 671โ€“677. https://doi.org/10.1136/bmjqs-2016-005849 โ†ฉ

  8. Ishikawa, K. (1976). Guide to Quality Control. Asian Productivity Organization. (Original Japanese edition 1968.) โ†ฉ

  9. Howard, R. A., & Matheson, J. E. (2005). Influence diagrams. Decision Analysis, 2(3), 127โ€“143. https://doi.org/10.1287/deca.1050.0020 โ†ฉ

  10. Taleb, N. N. (2007). The Black Swan: The Impact of the Highly Improbable. Random House. โ†ฉ

Graduate Attributes

Directly developed

  • Critical Thinker: Readers evaluate the limitations of the Five Whys technique against evidence of its arbitrary stopping points before deciding whether to use it.
  • Collaborative: Readers consider how different professional roles such as developers and testers perceive distinct failure modes during risk identification.

Modelled on this page

  • Reflective: The text examines the assumptions behind standard checklists by noting how historical items like externally furnished components have shifted meaning over time.
  • Subject Specialist: Discipline-specific frameworks such as cause-event-consequence structures are applied to transform vague concerns into actionable risk statements.